8.11 Prolonged Suspension 托长的暂停

If the suspension under Sub-Clause 8.8 [Suspension of Work] has continued for more than 84 days, the Contractor may request the Employer's permission to proceed. If the Employer does not give permission within 28 days after being requested to do so, the Contractor may, by giving notice to the Employer, treat the suspension as an omission under Clause 13 [Variations and Adjustments] of the affected part of the Works. If the suspension affects the whole of the Works, the Contractor may give notice of termination under Sub-Clause 16.2 [Termination by Contractor].
如果第 8.8 款[暂时停工]所述的暂停已持续 84 天以上,承包商可以要求雇主允许继续施工。如在提出这一要求后 28 天内, 雇主没有给出许可, 承包商可以通知雇主, 将工程受暂停影响的部分视为根据第 13 条[变更和调整] 规定的删减项目。若暂停影响到整个工程,承包商可以根据第 16.2 款[由承包商终止]的规定发出终止的通知。

邵工——建筑结构工程师 Structural Engineer

建筑一网(www.jianzhu1.com)是一群同济大学毕业建筑和土木相关专业毕业的研究生和博士组成的技术团体。我们自2011年始即开始从事结构设计和研究工作, 积累了大量的研究成果和创新技术,并整理了对中国规范、FIDIC合同、欧洲规范和美国规范的总结笔记。此外, 团队还在结构产品领域有所研究,并推出了超薄夹层、板桁架、无檩网架、装配式厂房和装配式酒店等相关装配式产品。

Latest posts by 邵工——建筑结构工程师 Structural Engineer (see all)

百度未收录
分享:

邵工——建筑结构工程师 Structural Engineer

建筑一网(www.jianzhu1.com)是一群同济大学毕业建筑和土木相关专业毕业的研究生和博士组成的技术团体。我们自2011年始即开始从事结构设计和研究工作, 积累了大量的研究成果和创新技术,并整理了对中国规范、FIDIC合同、欧洲规范和美国规范的总结笔记。此外, 团队还在结构产品领域有所研究,并推出了超薄夹层、板桁架、无檩网架、装配式厂房和装配式酒店等相关装配式产品。

发表评论

电子邮件地址不会被公开。