FIDIC合同全文翻译与条文理解系列(76)—— 8.1 Commencement of Works 工程的开工

by 邵工——建筑结构工程师 Structural Engineer |2017年7月16日 | FIDIC合同, 一带一路
[隐藏]
一起学FIDIC合同

一起学FIDIC合同

8 Commencement, Delays and Suspension 开工、延误和暂停

 

8.1 Commencement of Works 工程的开工

Unless otherwise stated in the Contract Agreement:
除非合同协议书另有说明:

(a)the Employer shall give the Contractor not less than 7 days' notice of the Commencement Date; and
雇主应在不少于 7 天前向承包商发出开工日期的通知;

(b) the Commencement Date shall be within 42 days after the date on which the Contract comes into full force and effect under Sub-Clause 1.6 [Contract Agreement].
开工日期应在第 1.6 款[合同协议书]规定的合同全面实施和生效日期后 42 天内

The Contractor shall commence the design and execution of the Works as soon as is reasonably practicable after the Commencement Date, and shall then proceed with the Works with due expedition and without delay.
承包商应在开工日期后,在合理可能情况下尽早开始工程的设计和施工,随后应以正当速度,不拖延地进行工程。

解读:

和国内合同一样,记住关键的时间节点。

邵工——建筑结构工程师 Structural Engineer

建筑一网(www.jianzhu1.com)是一群同济大学毕业建筑和土木相关专业毕业的研究生和博士组成的技术团体。我们自2011年始即开始从事结构设计和研究工作, 积累了大量的研究成果和创新技术,并整理了对中国规范、FIDIC合同、欧洲规范和美国规范的总结笔记。此外, 团队还在结构产品领域有所研究,并推出了超薄夹层、板桁架、无檩网架、装配式厂房和装配式酒店等相关装配式产品。

Latest posts by 邵工——建筑结构工程师 Structural Engineer (see all)

百度已收录
分享:

邵工——建筑结构工程师 Structural Engineer

建筑一网(www.jianzhu1.com)是一群同济大学毕业建筑和土木相关专业毕业的研究生和博士组成的技术团体。我们自2011年始即开始从事结构设计和研究工作, 积累了大量的研究成果和创新技术,并整理了对中国规范、FIDIC合同、欧洲规范和美国规范的总结笔记。此外, 团队还在结构产品领域有所研究,并推出了超薄夹层、板桁架、无檩网架、装配式厂房和装配式酒店等相关装配式产品。

发表评论

电子邮件地址不会被公开。