FIDIC合同全文翻译与条文理解系列(15)——2.1 Right of Access to the Site 现场进入权

by 邵工——建筑结构工程师 Structural Engineer |2017年7月15日 | FIDIC合同, 一带一路
[隐藏]
FIDIC合同-121x75

一起学FIDIC合同

2.1 Right of Access to the Site 现场进入权

The Employer shall give the Contractor right of access to, and possession of, all parts of the Site within the time (or times) stated in the Particular Conditions. The right and possession may not be exclusive to the Contractor. If, under the Contract, the Employer is required to give (to the Contractor) possession of any foundation, structure, plant or means of access, the Employer shall do so in the time and manner stated in the Employer's Requirements. However, the Employer may withhold any such right
or possession until the Performance Security has been received.
雇主应在专用条件中规定的时间(或几个时间)内,给承包商进入和占用现场各部分的权利。此项进入和占用权可不为承包商独享。如果根据合同,要求雇主(向承包商)提供任何基础、结构、生产设备或进入手段的占用权,雇主应按雇主要求中规定的时间和方式提供。 但雇主在收到履约担保前,可保留上述任何进入或占用权,暂不给予。
If no such time is stated in the Particular Conditions, the Employer shall give the Contractor right of access to, and possession of, the Site with effect from the Commencement Date.
如果在专用条件中没有规定上述时间,雇主应自开工日期起给承包商进入和占用现场的权利。
If the Contractor suffers delay and/or incurs Cost as a result of a failure by the Employer to give any such right or possession within such time, the Contractor shall give notice to the Employer and shall be entitled subject to Sub-Clause 20.1 [Contractor's Claims] to:
如果雇主未能及时给承包商上述进入和占用的权利,使承包商遭受延误和(或)招致增加费用,承包商应向雇主发出通知,根据第 20.1 款[承包商的索赔]的规定有权要求:

(a) an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], and
根据第 8.4 款[竣工时间的延长]的规定,如果竣工已或将受到延误,对任何此类延误,给予延长期;
(b) payment of any such Cost plus reasonable profit, which shall be added to the Contract Price.
任何此类费用和合理利润,应加入合同价格,给予支付。
After receiving this notice, the Employer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine these matters.
在收到此通知后,雇主应按照第 3.5 款[确定]的规定,就此项要求做出商定或确定。
However, if and to the extent that the Employer's failure was caused by any error or delay by the Contractor, including an error in, or delay in the submission of, any of the Contractor's Documents, the Contractor shall not be entitled to such extension of time, Cost or profit.
但是,如果出现雇主的违约是由于承包商的任何错误或延误,包括在任何承包商文件中的错误或提交延误造成的情况,承包商应无权得到上述延长期、费用或利润。

解读:

这一条是雇主给予承包商进入现场权利的相关事项。

承包商进入现场,意味着现场照管权的移交。移交事项主要包括以下一些内容:承包商占用场地的雇主书面确认;承包商进入工程现场的道路使用权的确认;施工用水、用电线路照管权移交及表初读数雇主、工程师、承包商的三方书面确认;控制性市政点位书面移交;地下管线及周边环境照管责任的移交等。国内很多承包商在进场的时候甚至会忘记施工水电的表初读数确认等的移交程序,这个就不应该了。

现场进入权须经雇主同意这一条的规定,也意味着现场进入有可能是在雇主安排下以某种部分或批次的方式进行。这种情况很常见。比如桩基施工场地只能分批移交,总承包也只能依此现实安排为逐步进场;总承包逐步交出单体及单体的室内部分工程,装饰施工单位才能逐步接收,开展装修施工。显然,这些“有计划安排”的现场进入会对承包商工程施工安排带来诸多限制,会直接影响中标人的承诺,所以分批接收现场应该作为招标人的投标要求来仔细安排,以避免双方可能在这个方面产生争议。

在本条内出现了利润与费用索赔的条款规定,招标人可以取消这一项作为投标要求。

邵工——建筑结构工程师 Structural Engineer

建筑一网(www.jianzhu1.com)是一群同济大学毕业建筑和土木相关专业毕业的研究生和博士组成的技术团体。我们自2011年始即开始从事结构设计和研究工作, 积累了大量的研究成果和创新技术,并整理了对中国规范、FIDIC合同、欧洲规范和美国规范的总结笔记。此外, 团队还在结构产品领域有所研究,并推出了超薄夹层、板桁架、无檩网架、装配式厂房和装配式酒店等相关装配式产品。

Latest posts by 邵工——建筑结构工程师 Structural Engineer (see all)

百度已收录
分享:

邵工——建筑结构工程师 Structural Engineer

建筑一网(www.jianzhu1.com)是一群同济大学毕业建筑和土木相关专业毕业的研究生和博士组成的技术团体。我们自2011年始即开始从事结构设计和研究工作, 积累了大量的研究成果和创新技术,并整理了对中国规范、FIDIC合同、欧洲规范和美国规范的总结笔记。此外, 团队还在结构产品领域有所研究,并推出了超薄夹层、板桁架、无檩网架、装配式厂房和装配式酒店等相关装配式产品。

发表评论

电子邮件地址不会被公开。