FIDIC合同全文翻译与条文理解系列(123)——14.5 Plant and Materials intended for the Works 拟用于工程的生产设备和材料

by 邵工——建筑结构工程师 Structural Engineer |2017年7月16日 | FIDIC合同, 一带一路
[隐藏]
FIDIC合同-121x75

一起学FIDIC合同

14.5 Plant and Materials intended for the Works 拟用于工程的生产设备和材料

If the Contractor is entitled, under the Contract, to an interim payment for Plant and Materials which are not yet on the Site, the Contractor shall nevertheless not be entitled to such payment unless:
如果根据合同规定,承包商有权获得尚未运到现场的生产设备和材料的期中付款,承包商必须具备下列条件才有权得到:

(a)the relevant Plant and Materials are in the Country and have been marked as the Employer's property in accordance with the Employer's instructions; or
相关生产设备和材料在工程所在国,并已按雇主的指示,标明是雇主的财产;或

(b)the Contractor has delivered, to the Employer, evidence of insurance and a bank guarantee in a form and issued by an entity approved by the Employer in amounts and currencies equal to such payment. This guarantee may be in a similar form to the form referred to in Sub-Clause 14.2 [Advance Payment] and shall be valid until the Plant and Materials are properly stored on Site and protected against loss, damage or deterioration.
承包商已向雇主提交保险的证据和经雇主批准的实体按批准的格式签发的、数额和币种与该项付款相同的银行保函。该保函可以用与第 14.2 款 [预付款] 中提到的格式相似的格式, 并应做到在
生产设备和材料已在现场妥善储存并做好防止损失、损害或变质的保护以前一直有效。

邵工——建筑结构工程师 Structural Engineer

建筑一网(www.jianzhu1.com)是一群同济大学毕业建筑和土木相关专业毕业的研究生和博士组成的技术团体。我们自2011年始即开始从事结构设计和研究工作, 积累了大量的研究成果和创新技术,并整理了对中国规范、FIDIC合同、欧洲规范和美国规范的总结笔记。此外, 团队还在结构产品领域有所研究,并推出了超薄夹层、板桁架、无檩网架、装配式厂房和装配式酒店等相关装配式产品。

Latest posts by 邵工——建筑结构工程师 Structural Engineer (see all)

百度未收录
分享:

邵工——建筑结构工程师 Structural Engineer

建筑一网(www.jianzhu1.com)是一群同济大学毕业建筑和土木相关专业毕业的研究生和博士组成的技术团体。我们自2011年始即开始从事结构设计和研究工作, 积累了大量的研究成果和创新技术,并整理了对中国规范、FIDIC合同、欧洲规范和美国规范的总结笔记。此外, 团队还在结构产品领域有所研究,并推出了超薄夹层、板桁架、无檩网架、装配式厂房和装配式酒店等相关装配式产品。

发表评论

电子邮件地址不会被公开。