FIDIC合同全文翻译与条文理解系列(108)——12.3 Retesting 重新试验

by 邵工——建筑结构工程师 Structural Engineer |2017年7月16日 | FIDIC合同, 一带一路
[隐藏]
一起学FIDIC合同

一起学FIDIC合同

12.3 Retesting 重新试验

If the Works, or a Section, fail to pass the Tests after Completion:
如果工程或某分项工程未能通过竣工后试验:

(a) sub-paragraph (b) of Sub-Clause 11.1 [Completion of Outstanding Work and Remedying of Defects] shall apply, and
应适用第 11.1 款[完成扫尾工作和修补缺陷](b)项;
(b) either Party may then require the failed Tests, and the Tests after Completion on any related work, to be repeated under the same terms and conditions.
任一方即可要求按相同条款和条件重新进行此项未通过的试验和任何相关工程的竣工后试验。

If and to the extent that this failure and retesting are attributable to any of the matters listed in sub-paragraphs (a) to (d) of Sub-Clause 11.2 [Cost of Remedying Defects] and cause the Employer to incur additional costs, the Contractor shall subject to Sub-Clause 2.5 [Employer's Claims] pay these costs to Employer.
如果此项未通过试验和重新试验是由第 11.2 款[修补缺陷的费用](a)至(d)项所列任何事项造成的,达到致使雇主增加费用的程度,承包商应根据第 2.5 款[雇主的索赔]的规定项雇主支付这些费用。

 

邵工——建筑结构工程师 Structural Engineer

建筑一网(www.jianzhu1.com)是一群同济大学毕业建筑和土木相关专业毕业的研究生和博士组成的技术团体。我们自2011年始即开始从事结构设计和研究工作, 积累了大量的研究成果和创新技术,并整理了对中国规范、FIDIC合同、欧洲规范和美国规范的总结笔记。此外, 团队还在结构产品领域有所研究,并推出了超薄夹层、板桁架、无檩网架、装配式厂房和装配式酒店等相关装配式产品。

Latest posts by 邵工——建筑结构工程师 Structural Engineer (see all)

百度未收录
分享:

邵工——建筑结构工程师 Structural Engineer

建筑一网(www.jianzhu1.com)是一群同济大学毕业建筑和土木相关专业毕业的研究生和博士组成的技术团体。我们自2011年始即开始从事结构设计和研究工作, 积累了大量的研究成果和创新技术,并整理了对中国规范、FIDIC合同、欧洲规范和美国规范的总结笔记。此外, 团队还在结构产品领域有所研究,并推出了超薄夹层、板桁架、无檩网架、装配式厂房和装配式酒店等相关装配式产品。

发表评论

电子邮件地址不会被公开。